Posted on: October 14, 2020 | Whiteshell News
The WCA has recently received the following information about road work in the park.
Falcon South Shore Road Project
- Nelson River Construction had labour issues (Sept 24th) which caused two interruptions in the work.
- This was resolved & work commenced again on Oct 5th.
- Crews will be taking three days off for Thanksgiving & then going 7 days a week until completion weather permitting
- Still intend to fully complete by end of October.
North Whiteshell Access Road graveling
ER77 at Brereton was completed in September
Update Oct 7, 2020 – “We planned on graveling as many cottage roads this year as our budget allowed but due to increased usage and costs we had to scale back the amount of the gravel contract. Our plan for the next operating seasons are to keep graveling roads to the south until they are complete. Once roads are done to the south we will look to gravel roads to the west from 307,309 junction.”